CONSTRUCTION SITE RIFLESSI DEL LAGO
Construction site access road: November 2023
Riflessi del Lago
Test drilling: November 2023
Riflessi del Lago
Demolition of the existing villa: December 2023
Riflessi del Lago
Excavation support works: February 2024
Riflessi del Lago
Excavation support works: March 2024
Riflessi del Lago
Excavation support works 2: May 2024
Riflessi del Lago
Excavation support works 3: May 2024
Riflessi del Lago
Excavation support works 4: June 2024
Riflessi del Lago
Excavation support works 5: July 2024
Riflessi del Lago
Excavation support works 6: July 2024
Riflessi del Lago
Excavation support works 7: August 2024
Riflessi del Lago
Excavation support works 8: August 2024
Riflessi del Lago
Excavation support works 9: September 2024
Riflessi del Lago
Excavation support works 10: October 2024
Riflessi del Lago
Excavation support works 11: November 2024
Riflessi del Lago
Completion of excavation works: December 2024
Riflessi del Lago
First section of the foundation slab poured: December 2024
Riflessi del Lago
Geothermal probe drilling (12 × 125 m): December 2024
Riflessi del Lago
Crane installation: December 2024
Riflessi del Lago
Second crane installation: February 2025
Riflessi del Lago
Basement level -2 slab: February 2025
Riflessi del Lago
Basement level -1, view from the ground floor: March 2025
Riflessi del Lago
Ground floor: June 2025
Riflessi del Lago
Ground floor: June 2025
Riflessi del Lago
First floor: July 2025
Riflessi del Lago
Penthouse floor: October 2025
Riflessi del Lago
Structural shell completed: March 2026
Riflessi del Lago